Friday, November 30, 2007

Friday's Update

Here's the updates for Friday, and things continue to move along smoothly. Considering that there are more building inspectors with more time on their hands to slow the process down, our contractor appears to be doing most things right the first time. Inspections that fail are quickly fixed and readied for the final phase of that project's inspection. I have posted some more pictures below that will show the progress. Fixing water damege from the stucco and brick drive-thru wall
This wall is framed in the area where the ice machine will sit in the new kitchen.




The storage out buildng is being connected to the restaurant's main building, making us just one building. The foundation is laid, and the block is being prepared.



We're installing new, energy efficient signs. No more freon. All LED lights make them more energy efficient and easier to maintain.





New tile in the restrooms is being installed. Early next week the fixtures will be put in place.

We're still ahead of schedule, and looking good for a mid December opening. It's all for YOU!

See you Soon